Project Overview
The homeowners contacted Pro Build Solutions because their existing 100-amp electrical service had reached its practical capacity. The existing 20-space panel had no remaining room for the additional electrical loads they were considering, including future kitchen improvements, a hot tub, sauna, EV charging, and garage upgrades.
The existing electrical service was already underground and ran approximately 80 feet from a ComEd pedestal to the rear of the house. The service equipment was reported to be original to the older home and included an Arrow Hart Murray panel that was full, showed corrosion, and lacked the grounding and exterior disconnect configuration planned for the upgraded system.
Pro Build Solutions performed a residential load calculation and developed a 200-amp service upgrade designed to provide substantially more panel capacity while retaining the property's underground service arrangement.
The project included electrical design, load calculation, permit documentation, utility coordination, excavation, underground conduit and conductors, new service equipment, a new 200-amp Siemens panel, grounding and bonding improvements, inspections, concrete restoration, grading, and reseeding.
Project Details
- Location
- Wood Dale, Illinois
- Project Type
- 200-Amp Underground Service Upgrade
- Existing Service
- 100A / 20-Space Panel
- New Service
- 200A
- New Panel
- Siemens 200A / 40-Space
- Underground Run
- Approximately 80'
- Underground Raceway
- 3" Schedule 40 PVC
- Service Conductors
- 3/0 Copper
- Trench Depth
- Approximately 18"
- Service Disconnect
- 200A Exterior Disconnect
- Surge Protection
- 35kA
- Grounding
- Two New Ground Rods + Water Bond
- Utility
- ComEd
- Active Construction
- Approximately 5 Working Days
- Power Interruption
- Approximately 4–6 Hours
- Project Investment
- $7,000–$9,000
Project Goals
- Increase the home's electrical service capacity from 100 amps to 200 amps.
- Replace the existing full 20-space panel with a larger service panel offering additional circuit capacity.
- Provide capacity for future electrical loads including a hot tub, sauna, EV charger, kitchen renovation, and garage improvements.
- Replace the existing underground service conductors with a new service installed in conduit.
- Upgrade grounding and bonding as part of the service replacement.
- Add an exterior service disconnect.
- Install whole-home surge protection as part of the new service equipment.
- Coordinate the service upgrade with ComEd, Wood Dale permitting, and required municipal inspections.
- Minimize the homeowner's power outage by completing the underground and exterior work before the final service cutover.
- Restore the concrete, grading, and lawn areas disturbed during underground installation.
Before & After
Compare the existing conditions with the completed project.
Before: The existing underground service supplied a 100-amp, 20-space panel that had reached capacity and limited additional electrical loads.
After: The upgraded service includes 200-amp equipment, an exterior disconnect, surge protection, updated grounding, and additional electrical capacity.
The Challenge
The primary challenge was not converting the property from overhead to underground service. The home already had an underground electrical service, but the existing system no longer provided the capacity the homeowners needed.
The original 100-amp, 20-space panel was full and showed corrosion, leaving limited ability to accommodate additional circuits or larger future loads. The existing service also required grounding and bonding upgrades as part of the replacement.
Replacing the underground service required following an approximately 80-foot route from the rear of the house to the existing ComEd pedestal. Portions of the existing service had been buried without conduit, and the new route passed behind a pine tree and beneath a section of the existing concrete patio.
Approximately 3 feet by 16 feet of concrete had to be removed to establish the new underground raceway. The project also required coordination with ComEd for the service upgrade and final cutover. Although active construction required approximately five working days, utility scheduling extended the overall project timeline by nearly three months.
Our Approach
Size the Upgrade Around Current and Future Loads
Pro Build Solutions completed a residential load calculation before finalizing the new service size. The existing 100-amp service was already limited, and the homeowners were planning additional loads including a hot tub, sauna, EV charger, kitchen renovation, and future garage improvements. A 200-amp service and larger panel were selected to provide additional capacity and reduce future limitations.
Replace the Existing Underground Service Route
The property was already served underground from a ComEd pedestal approximately 80 feet from the house. The replacement service followed that general route using a new 3-inch Schedule 40 PVC raceway installed approximately 18 inches deep with 3/0 copper service conductors.
Coordinate the Project With ComEd
Pro Build Solutions submitted the service-upgrade request, coordinated with ComEd, supplied and installed the underground conduit and customer-side service conductors, and prepared the system for the utility connection. ComEd supplied the utility-side equipment and completed its portion of the final service connection.
Build the Underground Infrastructure Before Cutover
Most exterior work was completed while the original underground service remained energized. This allowed trenching, conduit installation, underground inspection, concrete restoration, exterior service equipment, and other preparation to be completed before the homeowner experienced a power interruption.
Upgrade the Service Equipment
The existing 100-amp panel was replaced with a 200-amp Siemens 40-space panel. The new service also included an exterior disconnect, 35kA surge protection, properly identified transferred branch circuits, and additional panel capacity for future electrical work.
Upgrade Grounding and Bonding
The service replacement included two new interconnected grounding electrodes, bonding of the metal water service, and bonding at the service equipment. The original service was bonded only to the metal water main; the two grounding electrodes were added as part of the upgrade.
Minimize the Final Power Outage
The new underground and exterior service infrastructure was completed before the scheduled ComEd cutover. Panel replacement began early on the scheduled service day so the electrical transition could be completed within approximately four to six hours.
Restore the Property After Underground Work
The underground route required removal of approximately 3 feet by 16 feet of existing concrete. After the service installation and inspections, the concrete was repoured over a new gravel base, disturbed areas were graded, and the lawn was reseeded.
Scope of Work
- Residential electrical load calculation and 200-amp service design.
- Electrical permit drawings and documentation.
- Wood Dale permit and inspection coordination.
- ComEd service-upgrade coordination and scheduling.
- JULIE/811 utility locating before excavation.
- Removal of approximately 3' × 16' of existing concrete to access the underground service route.
- Excavation of an approximately 80-foot underground service trench.
- Installation of 3-inch Schedule 40 PVC underground service conduit.
- Installation of 3/0 copper service conductors.
- Installation of red underground electrical warning tape above the raceway.
- Preparation of service conductors at the existing ComEd pedestal.
- Installation of new 200-amp exterior service equipment and disconnect.
- Installation of a 200-amp Siemens 40-space electrical panel.
- Transfer and labeling of existing branch circuits into the new panel.
- Installation of 35kA surge protection.
- Installation of two new interconnected grounding rods.
- Bonding of the metal water service.
- Bonding at the new service equipment.
- Replacement of the garage feeder with a new 1-inch conduit for future subpanel or EV-charging capability.
- Underground electrical inspection.
- Electrical service inspection.
- Electrical rough inspection.
- Electrical final inspection.
- Building final inspection.
- Coordination of ComEd disconnect and reconnection.
- Concrete replacement over a new gravel base.
- Final grading and lawn reseeding.
Project Progress
Key stages showing how the project progressed from the existing conditions through the work and final installation.
Planning & Load Calculation
The service upgrade began with a residential load calculation to evaluate current demand and planned future electrical loads before selecting the new service size.
Trenching & Underground Raceway
Approximately 80 feet of new 3-inch Schedule 40 PVC conduit was installed from the rear of the house toward the existing ComEd pedestal, replacing the previous underground service route with a protected raceway.
Service Conductiors & Utility Connection
3/0 copper service conductors were pulled through the new raceway and prepared at the ComEd pedestal. The trench remained open for the required underground inspection before backfilling.
200 Amp Service & Panel Installation
The new service included a 200-amp exterior disconnect, Siemens 40-space panel, 35kA surge protection, updated grounding and bonding, and transfer and labeling of the home's existing branch circuits.
Utility Cutover & Site Restoration
The original service remained active while the new infrastructure was prepared. The final ComEd cutover and panel replacement limited the power interruption to approximately four to six hours, after which the concrete, grade, and lawn were restored.
Completed Project
Finished views and details from the completed project.
Project Outcome
The completed service upgrade increased the home's electrical capacity from 100 amps to 200 amps and replaced the full 20-space panel with a substantially larger 40-space Siemens panel.
The upgraded system provides additional breaker capacity for the homeowners' planned electrical improvements, including a future hot tub, sauna, EV charger, kitchen renovation, garage upgrades, and other expansion.
The existing underground service arrangement was retained, but the approximately 80-foot service run was rebuilt using a new underground conduit system and new service conductors. The new installation also added an exterior disconnect, surge protection, updated grounding and bonding, and clearly labeled transferred branch circuits.
A new 1-inch conduit was also installed for the garage feeder to provide flexibility for a future garage subpanel or EV-charging installation.
Most of the new service infrastructure was constructed before the scheduled utility cutover, limiting the final power interruption to approximately four to six hours. After electrical work and inspections were completed, the removed concrete was repoured, disturbed areas were graded, and the lawn was reseeded.
The homeowner ultimately gained the additional panel and service capacity that prompted the project while also leaving the property better prepared for future electrical improvements.
Related Resources & Services
Planning a Similar Project?
Tell us what you're planning and we can help you understand the next steps.
Start Your Quick Estimate